Monthly project update
June 2020
WORK ACTIVITIES:
- Started the Project
- Site
- Site has been stripped
- Started sub work for parking lots and roads
- Placed Electrical conduits
- Building
- Excavated building footings
- Poured concrete footings & foundations
- Backfilled building footings & foundations
- Started below slab MEP’s
- Site
UPCOMING ACTIVITIES:
- Site
- Finish Sub work of parking lots and roads
- Building
- Continue below slab MEP’s
- Prep for interior footings and slabs
- Start CMU
- Potentially start pouring concrete slabs
PROJECT SCHEDULE:
4%
Percent Complete
This project is being built for Sugar-Salem School District No. 322
|
This project is being built by Headwaters Construction Company
|
This project was designed by JRW & Associates
|
|