Monthly project update

AUGUST 2020

Previous Month
Month List
Next Month

WORK ACTIVITIES:
  • Started the Project
    • Site
      • Started laying water main line
    • Building
      • Interior footings have been completed
      • Below slab CMU has been completed
      • Below slab MEPs are almost complete
      • Poured concrete slabs in Area D & E
      • Started framing exterior walls in Area E
UPCOMING ACTIVITIES:
  • Site
    • Continue laying the water main line
  • Building
    • Finish exterior framing through Area’s D & E, start framing exterior wall in Area C
    • Start interior masonry in Areas D & E
    • Finish slab prep in area A & B
    • Pour slabs in Area A, B, & C
    • Start roughing in Electrical & Plumbing
PROJECT SCHEDULE:
13%
Percent Complete
This project is being built for Sugar-Salem School District No. 322
SugarSalem.org
This project is being built by ​Headwaters Construction Company
HeadwatersCC.com
This project was designed by ​JRW & Associates
JRWA.COM

This website has been created to provide construction project updates only and is not a part of Sugar-Salem School District's website and is not managed by the District or any District personnel.  

CONTACT US
Please submit any questions or comments regarding this project through the Contact Portal.
  • Home
  • Contact
  • District Transparency Report