Monthly project update
AUGUST 2020
WORK ACTIVITIES:
- Started the Project
- Site
- Started laying water main line
- Building
- Interior footings have been completed
- Below slab CMU has been completed
- Below slab MEPs are almost complete
- Poured concrete slabs in Area D & E
- Started framing exterior walls in Area E
- Site
UPCOMING ACTIVITIES:
- Site
- Continue laying the water main line
- Building
- Finish exterior framing through Area’s D & E, start framing exterior wall in Area C
- Start interior masonry in Areas D & E
- Finish slab prep in area A & B
- Pour slabs in Area A, B, & C
- Start roughing in Electrical & Plumbing
PROJECT SCHEDULE:
13%
Percent Complete
This project is being built for Sugar-Salem School District No. 322
|
This project is being built by Headwaters Construction Company
|
This project was designed by JRW & Associates
|
|
This website has been created to provide construction project updates only and is not a part of Sugar-Salem School District's website and is not managed by the District or any District personnel. |
Please submit any questions or comments regarding this project through the Contact Portal.
|